South Pars Gas Filed Development SPD-14D

The SPD 14-D platform includes the steps of pre-commissioning monitoring, Hook Up and commissioning, Start Up and Performance Test and operation.

Project specifications:

  • Main employer: Pars Oil and Gas (POGC)
  • Main EPCC Contractor: Iran Marine Industrial Company (SADRA)
  • Platform weight: 2500 tons
  • Production capacity: 500 million cubic feet of gas
  • Project location: SADRA Yard (Bushehr) – South Pars field
  • Project start: 10/19/2017
  • Achievements: Carrying out commissioning operations in 16 days